FEMA Awards Nearly $1.4 M to BMC for COVID-19 Testing Costs

Print Story | Email Story
BOSTON — The Federal Emergency Management Agency (FEMA) will send almost $1.4 million to the Commonwealth of Massachusetts to reimburse the Berkshire Medical Center (BMC) for the cost of of testing the public and staff during the COVID-19 pandemic.
 
The $1,390,865 Public Assistance grant will reimburse the private 302-bed teaching hospital in Pittsfield affiliated with the University of Massachusetts Medical School for the cost of contracting to administer 22,968 COVID-19 tests between September 2020 and January 2021.
 
The hospital also purchased supplies such as lab coats, masks, gloves, and propane for the testing tent, and contracted to provide security and cleaning services.
 
"FEMA is pleased to be able to assist the Berkshire Medical Center with these costs," said FEMA Region 1 Regional Administrator Lori Ehrlich. "Providing resources for our partners on the front lines of the pandemic fight is critical to their success, and our success as a nation."
 

Tags: BHS,   BMC,   COVID-19,   


More Coronavirus Updates

Keep up to date on the latest COVID-19 news:


If you would like to contribute information on this article, contact us at info@iberkshires.com.

Pittsfield ConCom OKs Stairs at Pontoosuc Lake

By Brittany PolitoiBerkshires Staff

PITTSFIELD, Mass.— Shoreline access stairs are coming to the south side of Pontoosuc Lake. 

Last week, the Conservation Commission approved an amendment to the Order of Conditions for work at Pontoosuc Lake Park.  There will be two stair sets on the south shoreline, and additional bank stabilization. 

In 2025, the park's south side saw new stairs from the parking lot, a boardwalk, and other improvements.  Later phases of the project will enhance the north side of the park for swimming, and remedy a concrete barrier wall that is partially underwater. 

"Generally, what we're looking to do at Pontoosuc Lake Park is install some stair sets in two locations to help folks access from up above the bank, over the bank, and into the water," Parks, Open Space, and Natural Resources Manager James McGrath explained during the July 23 meeting. 

"We're sensitive to some of the issues that are currently existing on the bank, and we're also sensitive to some of the needs for lake recreation out there."

Stairs for water access will be placed on the shoreline at the beginning of the boardwalk, where it is highly eroded, and the second staircase will be at the extreme western end of the project area, which has around 100 feet of highly eroded bank. 

Additional brush layering will also stabilize the bank. 

An area near the boat ramp where live stakes were vandalized will see them replanted after the ConCom found some of the bank erosion was worse than believed on a site visit last year. 

The city originally proposed not replanting the area where live stakes were removed. 

View Full Story

More Pittsfield Stories