WILLIAMSTOWN, Mass. — Williams College last week got the green light from the town to replace a bridge in the trail system for Hopkins Forest.
Hopkins Forest Manager Elise Leduc-Fleming was in front of the Conservation Commission seeking an order of conditions to replace the bridge at the top of the nature area's upper loop trail, near the trailhead for the Birch Brook Trail.
"One of the three stringers [on the existing bridge] is cracked and broken," Leduc-Fleming said, referring to the beams that support the bridge under the walking surface. "When I arrived for my position in July, that's how I found the bridge. As a safety measure, we've used a bottle jack to get it back where it was, and I slid a rock underneath it. So it appears to be sound from the top. But it's not.
"And every portion of the existing bridge is rotting to the point where all the wood is soft. It's only a matter of time before more of it breaks."
The foot bridge carries walkers over the north branch of Birch Brook. It is 18 feet long and wide enough (8 feet) to also accommodate a Gator utility vehicle that the forest staff uses for trail maintenance.
"I'm proposing two structural changes," Leduc-Fleming said. "One is the stringers that support the bridge across the stream were native cut trees from right there, essentially, that were lowered into place. That means they were untreated. And they rotted fast.
"I did actually source locust [wood] that has been milled just on two sides. It's still not treated, but I think the locust wood will last a lot longer in this environment."
The forest manager also said she is working to find a more durable sill on which to rest the bridge.
Her preference is to find stone sills, but she said may have to resort to pressure-treated wood, like what was used originally.
"Wood on ground is something I'm trying to avoid, just because I'm hoping to extend the lifespan of this next version of the bridge we put in so I'm not back here in five or 10 years asking to do the same thing again," Leduc-Fleming said.
She told the Con Comm that the new locust beams already were on site as she made her presentation to the commission at its Nov. 14 meeting because the project is on a tight timeline.
"I have a small window before Thanksgiving to get this done, so I made a leap there," she said. "Thanksgiving happens, we close the forest for two weeks for hunting season. Then I lose all my students and winter happens.
"I don't want to leave the bridge in the state that it's in until next spring, so I'm really hoping we can pull this off the next couple of weeks."
The commissioners, after receiving assurances that the work would not impact the water resource area, granted a negative determination of applicability under the Wetlands Protection Act, allowing the college to proceed with the replacement without a full engineering study.
While Leduc-Fleming hopes the new bridge in Hopkins Forest will last for years to come, the Con Comm also had a temporary bridge on its docket last Thursday.
The owner of a residence at 214 Bressett Road in South Williamstown needs to replace a septic tank. But accessing the tank requires crossing a brook on the property.
Dante Cellana of A1 Septic and Sewer of North Adams, representing the homeowner, presented the request to the commission.
"We're looking to gain access across the brook by building a temporary bridge elevated out of the stream," Cellana said. "We'd have to really cross a a few times to get the tank across and get minimal materials for the base of a tank in there. And we'd just remove the temporary bridge over the stream."
Cellana said he planned to use 5-foot-by-20-foot crane mats to span the brook.
"If extra support is needed, we'd put a block in the center [of the bridge]," he said. "But we could try it and see how the bridge supports go. If it doesn't look like it would hold it, we could put blocks in the river if needed."
Town Conservation Agent Andrew Groff told the commissioners that he would be able to monitor the project when the bridge is laid to ensure that none of the work impacts the brook.
In other business, Select Board member Stephanie Boyd presented the commissioners with a proposed policy on evaluating Chapter 61 land decisions that the board is considering.
She explained that the proposed policy would add to the process already laid out in Massachusetts General Law when municipalities are faced with decisions on whether to exercise a right of first refusal to purchase land if and when it comes out of the Chapter 61 program.
Chapter 61 is a program that allows owners of undeveloped land to realize a tax saving in exchange for keeping the land open. An owner can convert the land back to unprotected status only after the municipality has an opportunity to purchase it or assign the purchase rights to a qualified land trust — as was done recently with a parcel on Oblong Road.
Currently, the law requires notification of the Planning Board and Con Comm, in addition to the Planning Board, when such a process begins But the law does not necessarily give other town bodies the right to weigh in before the Select Board makes the final decision.
"We're suggesting that the Agricultural Commission, the Historical Commission and probably the Affordable Housing Trust also be notified," Boyd said. "We're suggesting the Select Board should ask for input from all those committees, and those committees can choose to give input or not as they see fit. Thirdly, the Select Board [under state law] only needs to hold a public hearing if they're going to purchase the property. We're suggesting there should be a public hearing to determine what to do with the right of first refusal."
Essentially, the Select Board is proposing to codify the process that the elected officials pieced together when faced with a decision on the Oblong Road lot.
"This is an opportunity to come up with some procedures without having to face a time clock or something," Con Comm member Lauren Stevens said. "I think that's admirable. I also think the idea of creating procedures that will seem fair and thorough, as I do think these are, is excellent. This is a great way to go."
The commissioners did not take a formal vote to recommend the proposed policy, but Chair Philip McKnight told Boyd she could report back to the Select Board that the Con Comm generally agreed with the draft on the table.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
Williamstown Planners Green Light Initiatives at Both Ends of Route 7
By Stephen DravisiBerkshires Staff
WILLIAMSTOWN, Mass. — Jack Miller Contractors has received the town's approval to renovate and expand the abandoned gas station and convenience store property at the corner of Sand Springs Road and Simonds Road (Route 7) to serve as its new headquarters.
Last Tuesday, the Planning Board voted, 5-0, to approve a development plan for 824 Simonds Road that will incorporate the existing 1,300-square-foot building and add an approximately 2,100-square-foot addition.
"We look forward to turning what is now an eyesore into a beautiful property and hope it will be a great asset to the neighborhood and to Williamstown," Miller said on Friday.
Charlie LaBatt of Guntlow and Associates told the Planning Board that the new addition will be office space while the existing structure will be converted to storage for the contractor.
The former gas station, most recently an Express Mart, was built in 1954 and, as of Friday morning, was listed with an asking price of $300,000 by G. Fuls Real Estate on 0.39 acres of land in the town's Planned Business zoning district.
"The proposed project is to renovate the existing structure and create a new addition of office space," LaBatt told the planners. "So it's both office and, as I've described in the [application], we have a couple of them in town: a storage/shop type space, more industrial as opposed to traditional storage."
He explained that while some developments can be reviewed by Town Hall staff for compliance with the bylaw, there are three potential triggers that send that development plan to the Planning Board: an addition or new building 2,500 square feet or more, the disturbance of 20,000 square feet of vegetation or the creation or alteration of 10 or more parking spots.
Jack Miller Contractors has received the town's approval to renovate and expand the abandoned gas station and convenience store property at the corner of Sand Springs Road and Simonds Road (Route 7) to serve as its new headquarters. click for more
The Community Preservation Committee will meet on Tuesday to begin considering grant applications for the fiscal year 2027 funding cycle. click for more
Town Meeting will be held at Williamstown Elementary School for the first time since 2019 after a unanimous vote by the Select Board last Monday night. click for more
It is unknown just how steep, but Superintendent Joseph Bergeron tried to prepare the School Committee at its January meeting on Thursday.
click for more