North Adams Airport Sets Deadline For Cell Tower Project

By Jack GuerinoiBerkshires Staff
Print Story | Email Story

NORTH ADAMS, Mass. — The Airport Commission set a November deadline for Diamond Communications last week, accepting a contract extension on installing a cell tower through Nov. 25.

After that date, the commission wants some form of compensation.

This initial extension was built into the original contract, and commissioners had no objection to honoring it. However, Diamond's second request for a nine-month extension gave the board pause.

The airport accepted a bid from Diamond in 2024 to install a cellular tower on the airport campus. Diamond offered a $30,000-a-year lease with a scheduled 2.5 percent annual increase. Terms also included a $100,000 bonus and a percentage of the tower's gross revenue if it becomes fully leased out.

Shirin Everett of KP Law, who helped negotiate the original agreement for the airport, called into the meeting. She confirmed the project is on hold because Verizon, which plans to utilize the tower, has yet to commit money toward it. Everett said understands Verizon has potentially budgeted for the project in 2027.

This means that at the very earliest, Verizon might make a decision in mid-2027. Following a standard due diligence period, the airport likely would not begin receiving rent payments until 2028. Everett added that telecommunications projects are experiencing delays nationwide.

The situation did not sit well with Airport Commissioner William Hooper.

"Verizon is not ready to pull the trigger for Diamond, so they are at risk of not having their primary subtenant ready to go," Hooper said. "So my concern is, does Diamond have a real commitment to be able to do this?"

He added that Diamond currently has no financial commitment to the city, making him hesitant to hold potentially valuable land for them without receiving anything in return.

"I would hate to be reserving the rights of Diamond for a square inch of the airport if we don't have real commitment from them," Hooper said. "As I read the agreement, I don't like where I feel we are at the moment."

Everett stated that come Nov. 25, the city could grant another extension — this time accompanied by a request for compensation. She emphasized that Diamond is not entitled to anything beyond Nov. 25, though she noted that in prior conversations, Diamond was not open to providing substantial compensation.

If Diamond and the city simply allow the contract to expire, Diamond remains responsible for paying the city's legal fees, according to Everett. Furthermore, if Diamond eventually completes the process with the city, they must pay an automatic $100,000 to the airport.

Everett added that if the city decides to reopen the Request for Proposals (RFP) process, they would likely still be waiting until at least 2028.

"These leases, for whatever reason, are taking months and months ... it is really between a rock and a hard place," she said. "You can stay with the devil you know and hope it comes through, or we can choose someone else."

In related news regarding land use at the airport, the commission expressed interest in exploring the possibility of installing solar panels.

The Pittsfield Airport unveiled its own solar array in late September. The 17.7-acre solar field is expected to generate nearly $3 million over the next 20 years through lease payments and collected taxes.

"It was exciting for me too, so I am glad you are having this discussion," said Andrew Fitch, city councilor and liaison to the airport. "But I don't know how much land we need, how far away from the runway it needs to be."

Pittsfield's project has been underway since 2016, and the commission acknowledged that any similar development in North Adams would take time. They were also uncertain whether the city would incur costs to prepare the property for solar development.

Hooper noted that the topography of the North Adams airport is quite different from Pittsfield's, leaving him unsure how much land could be utilized and at what scale.

Hooper said he would reach out to the Pittsfield airport manager to initiate a discussion, hoping she might attend a future meeting to discuss solar options more in-depth with the full commission.

The commission officially approved the T-Hangar project, despite previous hesitation.

In September, commissioners were informed that the $1.622 million project was substantially over budget, requiring the airport to contribute $115,000. While the commission informally supported the project in September, they had not officially voted on it until now.


Tags: airport commission,   cell tower,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

McCann Making Progress Toward MCAS Targets

By Jack GuerinoiBerkshires Staff

NORTH ADAMS, Mass. — McCann Tech Principal Justin Kratz told the Northern Berkshire Vocational Regional School District School Committee last week that because the school is making substantial progress toward its 2026 MCAS targets, there will be no Massachusetts Department of Elementary and Secondary Education (DESE) intervention.

"So long story short, we are not on DESE's radar for MCAS performance," he said. "At the end of the day, that is what is what we are after."

Kratz said McCann scored "a ton" of points, showing growth in most categories. He said they earned 75 percent of total possible points for all students and 83 percent of all possible points for lowest-performing students.

Kratz noted that DESE tends to change targets and formulas every year. But he drew attention to the year 2025, when a passing MCAS score was no longer a graduation requirement. In 2025, McCann received 33 percent of the possible points and 7 percent for the lowest-performing students. This equaled a score of 20 percent.

"That was the year where everything went off the cliff," he said. "We didn't do very well. This year was 79 percent, and that is knocking it out of the park. ... If we followed up with another 20, we would have been in rough water."

Kratz added this drop was typical across the state, saying he assumed students just took the test less seriously. He wanted to demonstrate how the scores and targets are "reshuffled" and gave a closer look at English scores over the years.

In 2024, the school had a target of 499.3 (average scaled score). The school scored 500.4. In 2025, McCann's new target was 502.5, but McCann scored 485.6. McCann's 2026 target was 487.7, and they scored 486.8.

Kratz said McCann is not scoring as high as they were in 2024, but they are getting more points. He said sometimes the scores needed to be taken with a "grain of salt."

He underlined that although MCAS is important in a vocational education, it only represents half of what a student does in a given school year. 

"There is no MCAS for 50 percent of their time here, which is their trade area," Kratz said. "They [DESE] don't assess that ... so this one little pocket is important, but it doesn't show the entire picture of a student."

Kratz moved from what he called the "good" section of his presentation to the "awesome." He said McCann was recognized as one of 55 schools that drastically improved chronic absenteeism by at least 5 percentage points. He said the school received a letter from DESE congratulating them that included a survey that asked how the school did it.

"It was a nice letter, but we kind of laughed and asked, 'What did we do?' " he said. "I say that sort of tongue-in-cheek because we didn't do any sort of targeted attendance improvement initiative."

He said the more he thought about it, the more he attributed the change to standardized grading and improving the school environment physically and culturally.  

"We didn't do all that wanting to improve attendance. We did it because we wanted to create more equity, and ... I think that is a byproduct of that," Kratz said. "Kids are more likely to want to go to school if that 62 they got on a test does not bury them for the rest of the year. They know they can dig their way out of it. And they are more likely to go to school if the building is a little brighter when they walk in in the morning."

Also, the importance of attendance is baked into the vocational school experience.

View Full Story

More North Adams Stories