The School Building Committee opted to go with the post sign, but asked for changes to the font and graphics.
NORTH ADAMS, Mass. — The Greylock School Project has passed one of two local permitting authorities in preparation for bidding documents to be released Nov. 17.
The Conservation Commission gave the OK for the $65 million project on Tuesday.
"We're targeting a completion date for the documentation on Nov. 17," Jesse Saylor of TSKP Studio told the School Building Committee meeting just before the Conservation Commission. "The real reason that's later than we had anticipated is because of the local review meetings ... We have a Conservation Commission meeting, public hearing today, Oct. 21, at 6 p.m., that's what we're going to right after this meeting, and that will be our first time meeting with the Conservation Commission. ...
"We anticipate meeting with the Planning Board at a public hearing on Monday, Nov. 10. If we're approved to proceed at that meeting, will be ready to go to bid. And so we've set the bid date one week later, leaving a week if there are any amendments that are required to the documentation."
Saylor and Chelsea Christenson, a civil engineer with Nitsch Engineering, presented the plans to the commission.
"Our goal of the project is to bring nature to the students through the design of the school, also the building itself is a good environmental steward," said Saylor. The building systems are all electric. No fossil fuels are used to heat or cool the building. Energy models anticipate that the building will be highly energy-efficient thanks to its highly insulated walls and roof and also due to geothermal wells that will harvest the relative warmth of the earth in the winter and its coolness in the summer to offset human cooling loads."
The site itself "retains some natural resources worthy of protection," he said, including an intermittent stream that runs into a pipe on the southern edge and, to the north, there's a "more significant" wetlands area.
The stream will not be affected and the wetlands are part of the school drainage will continue to be fed that way. The project also is not expected to affect Well No. 2, a backup for the city's water system.
"The project will also conserve mature tree growth at the north edge of the site and at the south edge of the site, which creates a natural buffer to residential residential neighborhoods to the north and south," Saylor continued.
Con Com Chair Andrew Kawczakasked the city's Public Services Commissioner Timothy Lescarbeau, who was in attendance, if the plan met the wellhead protection requirements.
"The well is in a non-conforming zone to begin with, because it's close to the roads and you know the school, the old school," he said. "The area is much better now than it was considering GreylockWorks was an aluminum anodizing plant that always made me cringe. Now it's retail and rental space, residential, so I don't see any impact from this."
Christenson walked through the details for water drainage and catchment, noting "we did get a letter from DEP Water Resources supporting the project."
In response to questions, she and Saylor elaborated that the turtle pond is a manmade educational component and not part of the water management system.
"A lot of design and research has gone into this pond to make these turtles survive," Christenson said. "I know our landscape architects have done a lot of research on what they need and hibernation and all sorts of things. So it's been fascinating listening to it."
The turtle pond was a feature of the open courtyard in the old school that is being replicated in the new school. Saylor said it will be lined without about 3 feet depth of sand, though there are conversations about the depth because of the age of the children in prekindergarten-through-Grade 2 school.
Before the commission meeting, the School Building Committee narrowed down its choices on the main sign. The members had not liked the previous iterations, so TKSP came back with options incorporating their feedback.
"There's a attempt in both of these signs to kind of match up with the building in a little bit of an abstract way," said Saylor.
They were offered a modification of the post sign with straight rather than peaked top (Option 1) and a simpler sign using the vertical fiber cement siding planned for the school with a flat top (Option 3). Members liked the graphic on the post sign and the sided option but there were concerns it looked too much like a bench for hanging out. Several stated concerns on the font and the ability to read the lettering; Superintendent Timothy Callahan reminded them the signs would be about 8 feet long, which would be reflected in the letter.
"I want something that has a little bit more whimsy, that's a little bit more exciting, because, like, we're making this for them, like we want them to see the sign and get excited," said member Andrew Rosenburg, pitching for the post sign. "It's a nice time, but 3. That's I feel like it kind of goes towards more adult sensibilities."
The members voted for Option 1, the post sign, but asked for more work on the font and graphic.
The committee also voted to hire Energy Tax Savers Inc., a consulting firm specializing in green energy grants, to work on its federal geothermal financing.
Tim Alix of Collier's International, the owner's project manager, said it's been recommended by other districts and the Massachusetts School Building Authority to have a consultant because the applications will be completed after the system in operational.
"By having somebody work with us and assist us, we'll be requesting that the contractor document the costs and breakdowns in such a way that we have all that information available to us, and this consultant would then work with the district on assembling that application and submitting those those documents," he said.
Collier's sought three proposals and Energy Tax Savers was the lowest at $15,900 compared to the other two about $50,000 with alternative add-ons.
"I think that that would be the outfit to go with, the prices which is more reasonable, and we have experience of working with them, and things have gone well," Alix said.
If you would like to contribute information on this article, contact us at info@iberkshires.com.
Your Comments
iBerkshires.com welcomes critical, respectful dialogue. Name-calling, personal attacks, libel, slander or foul language is not allowed. All comments are reviewed before posting and will be deleted or edited as necessary.
No Comments
North Adams Clothing Store Moving to Larger Space
Staff Reports
NORTH ADAMS, Mass. — Label Shopper is moving across the parking lot to the former Peebles location in April.
The discount clothing store has been located in the downtown's L-shaped mall downtown since 2009. It replaced Fashion Bug, which had been in that spot for 24 years before closing in 2007; the company liquidated in 2013.
Label Shopper is part of Peter Harris Clothes, established in 1970 by Peter Elitzer. Starting as a single store in Latham, N.Y., offering brand-name apparel at discount prices, the company operates more than 70 stores throughout the Northeast and Midwest.
The store is set to close on April 6 for the move and reopen on April 9 in the former Gordmans, according to signage.
Gordmans briefly replaced Peebles in the former Kmart until the parent company of the two brands declared bankruptcy and closed its stores in 2020.
At 17,250 square feet, the Gordman's space is at least double the size of Label Shopper's current location.
For many years, the town of Lee has had to struggle with an outdated and crowded Police Department station located in its Town Hall, which was built in 1874. Its nearby fire station was originally constructed to house horse-drawn firefighting vehicles. click for more
The organization had successfully grown over the past 20 years and, by the end of the decade, would see its campaign drives pass the $100,000 mark and the number of agencies under its umbrella grow to 17. click for more
The City Council got an update on what's up in the school system and its president was inducted into the mayor's Women's Leadership Hall of Fame. click for more
The Massachusetts Museum of Contemporary Art Commission welcomed bread-baking appliance designers Brod & Taylor to the campus on Monday. click for more