Dalton Division Road Sewer Line Questioned

By Sabrina DammsiBerkshires Staff
Print Story | Email Story
DALTON, Mass. — As the engineering of projects for Dalton Division Road continue, some officials question the investment of a proposed sewer line. 
 
"The board has made a decision that they think it's appropriate to complete the sewer project, but we are talking about a pretty expensive project to tie in a fairly small number of homes," Town Manager Eric Anderson said during the Select Board meeting last week. 
 
"I'm not saying that's good or bad. I'm just saying that that needs to be considered, because we're going to need to be funding that." 
 
Installing a sewer line is probably going to be about a couple million-dollar project, but the town is probably a year away from knowing the final cost, he said. 
 
"I'm just nervous to be honest with you," Select Board member Antonio "Tony" Pagliarulo said. 
 
The town has a lot of capital projects that would favor a greater number of residents, not to take away from the Dalton and Pittsfield residents on the street, he said, 
 
The residents of Dalton Division Road have been promised that if the street was ever rebuilt that a sewer line would also be constructed, Select Board member John Boyle said. 
 
"This is why the Select Board, after a great deal of lobbying by the residents in that area, voted to pay for the engineering with [some of the] American Rescue Plan Act funds and to seek funding through grants and town participation in the construction of the sewer," he said. 
 
Although the town has made those promises, Pagliarulo said he is still hesitant to endorse it given the other capital projects the town is facing. 
 
"But let's see how it unfolds," he said. 
 
Select Board member Dan Esko said voters will have an opportunity to vote on whether to fund the sewer project during a town meeting once the cost is known. 
 
"If there is not an appetite for it then they will vote it down," he said. 
 
One mechanism of funding it is to transfer as much free cash into the project as it can into sewer stabilization so that "theoretically, in a couple of years" the town can fund it from the stabilization account, Anderson said. 
 
According to correspondence with Edward "Bud" Hall, Department of Public Works superintendent, the stabilization account needs at least $750,000 to respond to significant pumping station failure, or a failure of one of the large sewer lines, Anderson said. 
 
The state is reimbursing the town for the cost of the road and putting in a multi-use pathway, but the sewer project would be at the expense of the town, he said. 
 
"There may be grants available," Select Board Vice Chair John Boyle said. 
 
The Dalton Division Road project involves "significant" improvements to the 1.6-mile stretch. When the project was in 25 percent design last year, Dalton planners were mulling options for sidewalks, bike lanes, and other road measures. 
 
In November, Pittsfield entered into an intermunicipal agreement with Dalton to reconstruct Dalton Division Road. The agreement is for five years with the option to extend to eight years, or until the project is completed. 
 
Each municipality will be responsible for acquiring any necessary land interests and permits on its own soil. Dalton will cover appraisal costs and compensation for takings, and has agreed to indemnify Pittsfield against challenges to the takings. 
 
According to the state Department of Transportation's project page, this $13 million to $14 million project is planned to be funded through the 2028 Transportation Improvement Program for the Berkshire Metropolitan Planning Organization. Construction is set to begin in 2028, but the town has been told it  could "easily" slip to the 2030 construction season. 
 
The engineering for a proposed sewer line on Dalton Division Road is slightly ahead of its reconstruction, so the engineers at Fuss and O'Neill questioned whether the town wants to consider splitting the projects and constructing the sewer line a year ahead. 
 
The advantage of this approach is that the town can construct the sewer line, ensure it is fully functional and compacted, and then proceed with the roadwork, Anderson said. 
 
However, this is more expensive and would require the town to dig up the road two years in a row instead of completing the work all at once, he said. 
 
The decision to explore adding a sewer line to the Dalton Division Road project was discussed in 2022, as installing it after the road’s completion would be both difficult and wasteful.
 
During that meeting, it was said that there are 14 houses that would be impacted by the additional sewer line. Of the 14 houses along this line, 10 indicated an interest in connecting.
 
To connect, residents would have to pay $500. To actually connect to the line, property owners would have to pay an additional $75 per foot. 

Tags: sewer,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Fenton: Governor's Council Must Deliver for the Berkshires

Community submissionGuest Column
I am a Springfield lawyer running for Governor's Council and I am asking for Berkshire County residents to support me over an incumbent from North Adams. 
 
Here's why: Last year I learned about staffing issues in our regional courts that I could not ignore. In 2025, it was reported that four of Western Massachusetts' 11 Superior Court judgeships were vacant, all at the same time. A few weeks later, that grew to five vacancies. This meant there were only six Superior Court judges serving all of Western Mass at a time when Berkshire, Hampshire, Franklin, and Hampden counties had more than 100 pending homicide cases. 
 
Those numbers were alarming to me, so I started to engage with leaders in the community who work most closely with the court system and I came to learn that these vacancies were only the tip of the iceberg here in Berkshire County.
 
I learned that no Superior Court or District Court judge had been appointed from the Berkshires since the current incumbent took office. As a result, there is not a single Superior Court judge who lives in the Berkshires today, and several of the District Court judges drive in from other counties to support Berkshire courts in Pittsfield, Great Barrington, and North Adams. Court staff also informed me about severe staffing shortages at the Berkshire Clerk of Courts office resulting in other counties needing to loan staff to the Berkshires just so hardworking employees can take a brief and planned summer vacation. This is not normal. These issues are a reflection of genuine problems with the Berkshire County court system and show a lack of proactive attention from our Governor's Councilor.
 
Instead of focusing on regional equity, I watched as the current incumbent celebrated that she has voted against the governor's nominees more than any other councilor, without much explanation as to why. Most recently, she voted against two extremely qualified former prosecutors for the Parole Board. This was despite an in-person plea from the governor and a letter of support from all the three of the district attorney's from Western Mass. Those votes do not show independence or standing up for principles, they demonstrate naivete, and an unwillingness to work with the key stakeholders.
 
I had seen and heard enough. I decided to jump in the race and challenge the incumbent to address these problems head-on.
 
I am a partner of a regional law firm. I understand our courts and the importance of having qualified, fair and hardworking judges. And I know how important it is to have judges from the Berkshires serving the Berkshires. To achieve that, you need strong relationships with the legal community and local stakeholders. You need to know how to use the power of the Governor's Council to fight forcefully for our region. And you need to be laser focused on identifying vacancies before they occur so that they can be filled quickly with local candidates.
 
View Full Story

More Pittsfield Stories