Adams' Valley Street Shed Still Needs Funding

By Brian RhodesiBerkshires Staff
Print Story | Email Story

ADAMS, Mass. — Construction of the new shed at Valley Street Field may be delayed due to a lack of funding. 

 

Mike Benson of the Adams/Cheshire Little League attended Monday's Parks Commission meeting and said the league is still working on obtaining funds for the shed. The town appropriated $3,000 for the shed as part of the fiscal 2023 budget and asked the league to match. 

 

"I've done a ton of fundraising this year to try to keep the costs low for the kids," Benson said, noting he could probably contribute about half of the $3,000 needed right now.

 

The league, Benson said, is in the process of ordering a new scoreboard for the field, one similar to the one recently installed at Russell Field. He said financing the scoreboard came first, as it was in the works before planning for the new shed began. 

 

"We had started the scoreboard thing before we heard anything about the shed," he said. "... We haven't asked the town for anything to do to help with the scoreboard. We're doing it all on our own, it's $3,500." 

 

Mark Pizani, an equipment operator at DPW, said they would likely be able to get more time out of the old shed if the league needs more time for funding. Benson said he would happily work with the town to clean the shed. 

 

"We can work it out with what we have. If we need another year out of it, it's really not a big deal," Pizani said. "That's my personal feeling. It would have been nice to have." 

 

Commission Chair James Fassell agreed the current shed can keep being used and said the group will revisit the issue in the future. 

 

"I just want to make sure it's for the good of the league and for the good of Adams," he said. 

 

In other business, Pizani updated the board on a berm near Russell Field, which the group was concerned could overflow onto the field. He said a significant amount of brush and debris was removed from the water since the last meeting, making an overflow less likely. 

 

"We cleaned that whole river out," he said. "We cleaned it out; it's in good shape. We took truckloads of debris and stuff out of the river." 


Tags: parks commission,   

If you would like to contribute information on this article, contact us at info@iberkshires.com.

Greylock Glen Outdoor Center 90% Complete

By Tammy DanielsiBerkshires Staff
ADAMS, Mass. — The Greylock Glen Outdoor Center is about 90 percent finished with an anticipated completion date in August. 
 
Matthew Sturz of owner's project manager Colliers International updated the Selectmen on the project's progress via Zoom on Wednesday. 
 
"We'll work with the town to determine exactly the logistics of that," he said in response to questions about the opening. "I think that there's certainly interest in getting the facility open as soon as it can open. But we do need to conclude the construction activities ... it's not federally advisable to have construction activity going on with the public."
 
The completion will depend on getting a certificate of occupancy for the 10,000-square foot facility.
 
The  $8.3 million project is running eight months behind the expected schedule, Sturz said, largely because of permitting with the state Department of Environmental Protection that required an extensive environmental review of endangered species, working with National Grid to determine how solar will be integrated into the project, and the need for a water system for both potable water and fire suppression. 
 
"Transformers and all manner of electrical switchgear is being significantly impacted by supply chain issues throughout the construction industry," said Sturz. "So coordinating those items up front took a little bit longer than anticipated."
 
A 350,000-gallon water tank is being constructed on the grounds to provide water with completion expected by July or August. 
 
View Full Story

More Adams Stories